The construction of the Kingfisher and Francolin dams at Simbithi Eco Estate was completed on the 22 July 2011, just in time for another bout of heavy rain over the weekend that helped to fill the dams. Ramtar Construction lined both dams with Geosynthetic Clay Liners (GCLs), which is a specialist lining product.
After some set backs due to the unseasonally heavy rain storm we experienced in June, we are back on track with the lining installation to the dams at Simbithi Eco Estate. Below are some pictures of the lining installation.
Ramtar Construction has been appointed to construct the earthworks and dam linings for two ornamental dams at Simbithi Eco Estate. The project involves preparing and lining 4900 sq.m of dam floor area and will incorporate Geosynthetic Clay Liners (GCLs) as the barrier material. Commencement date: 20 April 2011.
|