Simbithi Eco Estate Dams - Completion

13/9/2011

3 Comments

 
The construction of the Kingfisher and Francolin dams at Simbithi Eco Estate was completed on the 22 July 2011, just in time for another bout of heavy rain over the weekend that helped to fill the dams. Ramtar Construction lined both dams with Geosynthetic Clay Liners (GCLs), which is a specialist lining product.
Picture
Kingfisher Dam
3 Comments

Simbithi Eco Estate Dams - Update

4/7/2011

2 Comments

 
After some set backs due to the unseasonally heavy rain storm we experienced in June, we are back on track with the lining installation to the dams at Simbithi Eco Estate. Below are some pictures of the lining installation.
2 Comments

Simbithi Eco Estate Dam Linings

14/4/2011

1 Comment

 
Ramtar Construction has been appointed to construct the earthworks and dam linings for two ornamental dams at Simbithi Eco Estate. The project involves preparing and lining 4900 sq.m of dam floor area and will incorporate Geosynthetic Clay Liners (GCLs) as the barrier material.  Commencement date: 20 April 2011.
1 Comment

    Author

    Managing member

    Archives

    August 2025
    March 2023
    June 2022
    April 2017
    November 2016
    November 2013
    June 2013
    May 2013
    July 2012
    September 2011
    July 2011
    April 2011
    March 2011
    August 2010

    Categories

    All
    Concrete Retaining Block Walls
    Dams
    Landfill Linings
    Lining Installation
    Projects
    Ramtar Construction
    Retaining Walls
    Website

    RSS Feed

Powered by Create your own unique website with customizable templates.
  • Home
  • Services
    • Civils
    • Building
    • MSE Walls
    • Retaining Walls
  • Projects
  • Contact Us